Builds and interrogates a project schedule — logic-driven sequencing, dependency types and lags, float and the critical path, resource loading and leveling, schedule risk analysis, and measuring progress against a baseline rather than against optimism. Use this to construct a schedule, audit one you have inherited, find out why a plan keeps slipping, work out what a date change actually costs, or judge whether a reported percentage complete means anything.

インストール方法を見る

含まれるファイル(2)

  • SKILL.md4.9 KB
  • references/sources.md983 B

SKILL.md(原文)

インストールする前に、エージェントに与えられる指示の中身を確認できます。

Schedule development and analysis

A schedule is a model of how work connects. Most schedules in circulation are a list of dates someone typed, which looks the same in a status deck and behaves completely differently when anything moves.

Build it from logic, not from dates

Every task except the first and last should be connected to something. A task with a date and no predecessor is an assertion; a task with a predecessor is a plan, because when the predecessor moves the task moves with it and the schedule tells you so.

  • Finish-to-start is the default and covers most real dependencies.
  • Start-to-start and finish-to-finish describe overlapping work honestly and are worth using rather than faking the overlap with an earlier date.
  • Lags should represent something real — curing time, a notice period, a review window. A lag used to make dates line up is a hidden assumption.

Hard-coded date constraints are where schedules go to die. Each one severs the logic at that point, so slippage upstream stops propagating and the schedule keeps reporting a date it can no longer support.

Float is the information, and the critical path is the consequence

Float is how long a task can slip before it moves the end date. The critical path is the chain with none. Attention belongs there and almost nowhere else — expediting work with three weeks of float buys nothing and consumes the same management capacity.

Two readings worth taking regularly: near-critical chains, which become critical after one bad week and are where surprises come from, and negative float, which means the schedule is already telling you the date is impossible and someone has not looked.

Load resources before you believe the dates

A schedule that assumes the same three people work on five parallel tasks is fiction that will resolve itself as a delay. Load the named constraint — the one team, the one approver, the one environment — and level it. Leveling extends the schedule; that extension was always there, it was just unrecorded.

Analyze schedule risk rather than adding a buffer at the end

Durations are ranges. Running the schedule with ranges rather than single durations shows something a buffer cannot: paths that merge. Where several chains converge on one milestone, the milestone waits for the latest of them, so the probability of hitting the date is far lower than the probability of any single chain hitting its own — which is why plans with many parallel workstreams slip even when no individual stream looks late.

A buffer at the end of the plan protects the end date. A buffer in front of each merge point protects the plan.

Measure progress against the baseline, not against effort

Keep a baseline and compare to it, or "we are 70% done" has nothing to be 70% of.

The useful comparison is three-way: what was planned to be complete by now, what is actually complete, and what it cost to get there. Those three answer different questions — the first two give you schedule performance, the last two give you cost performance, and a project can be ahead on one and badly behind on the other.

Percentage complete on in-progress work is where reporting rots. A task reported at 90% for three weeks is not 90% complete. Binary reporting — not started, in progress, done — with small enough tasks that "done" arrives often is more honest and takes less time to maintain.

Auditing a schedule you inherited

Look for these in order, because each one invalidates everything after it: tasks with no predecessor or successor, hard date constraints, negative float, durations longer than a reporting period, tasks that have been 90% complete for more than one period, and a baseline that has been re-set so often it no longer means anything.

Sources

references/sources.md in this skill lists the outside authorities that settle the questions here — what each one is authoritative for, and what you may do with it. Check them before answering on anything they cover, and cite what you used. Most are free to read and not free to reproduce; the use note on each is binding.

Never

  • Accept a date on a task with no logic behind it.
  • Hard-code a constraint to make a date hold. It stops the schedule from telling you the truth.
  • Report percentage complete on a task whose remaining work nobody has re-estimated.
  • Re-baseline to make variance disappear. Re-baseline when scope genuinely changed, and say which.

レビュー

まだレビューはありません。使ってみた感想をお寄せください。

同じリポジトリのスキル

概要と使いどころ

Designs and audits who can reach what — authentication, authorization models, privileged access, service credentials, and joiner-mover-leaver process. Use this to design a permissions model, run an access review, reduce standing privilege, handle offboarding, set up SSO or MFA, manage service and machine credentials, or diagnose why permissions have sprawled.

日本語の概要は準備中です。原文の説明を表示しています。

cbrock84/headcount2,0312026年9月18日 更新

Concentrates marketing and sales effort on a named set of accounts rather than on volume — qualifying whether the model fits your economics at all, building the account list and the buying group inside each, tiering effort against account value, coordinating so the account experiences one campaign rather than several, and measuring account progression instead of leads. Use this to decide whether to run an account-based program, build one, or work out why an existing one produces activity and no pipeline.

日本語の概要は準備中です。原文の説明を表示しています。

cbrock84/headcount2,0312026年9月18日 更新

Gets new users from signup to first real value — signup flow, onboarding, time-to-value, and the early experience that determines whether someone becomes a user or a lapsed account. Use this to design or fix signup and onboarding, diagnose why signups do not convert to active use, reduce time-to-value, or decide what a new user must accomplish first.

日本語の概要は準備中です。原文の説明を表示しています。

cbrock84/headcount2,0312026年9月18日 更新

Designs orchestrator-and-subagent hierarchies for a repository — splitting agents by exclusive write surface, pairing every producer with an independent auditor, and enforcing the split with a script that runs in CI. Use this whenever the user wants to set up, expand, audit, or fix a multi-agent or subagent structure for a codebase; asks how to divide work between agents; wants agent charters, roles, or a surface map written; or is hitting agents that collide on the same files, review their own work, or drift from their remit. Also use when sizing a roster or deciding whether a new agent is justified.

日本語の概要は準備中です。原文の説明を表示しています。

cbrock84/headcount2,0312026年9月18日 更新

Governs models and AI systems in production — intended use, evaluation, monitoring, human oversight, documentation, and the decision to deploy or retire. Use this before deploying a model or AI feature, when defining evaluation criteria, when a model's behavior has drifted, when assessing AI risk or regulatory exposure, or when deciding whether an AI system is fit for a consequential decision.

日本語の概要は準備中です。原文の説明を表示しています。

cbrock84/headcount2,0312026年9月18日 更新

Produces executive-level research — market sizing, competitor mapping, trend analysis, and strategic intelligence — grounded in cited sources with the confidence in each claim made explicit. Use this to analyze a market or industry, map competitors, evaluate a market-entry or build-versus-buy decision, produce a research brief, or assemble evidence for a decision. Also use when comparing options that need a structured, evidence-based verdict rather than an opinion.

日本語の概要は準備中です。原文の説明を表示しています。

cbrock84/headcount2,0312026年9月18日 更新

cbrock84 のスキルをすべて見る

このスキルの問題を報告する