Write a structured weekly or bi-weekly program status report for stakeholders. Use when the user says "write a status report", "program update", "stakeholder update", "weekly status", "RAG status", "program health report", "what do I send to leadership", "write the update for [program]", or needs to communicate delivery progress - even if they don't explicitly say "status report". Produces a concise, scannable report with RAG status, blockers, and decisions needed.

インストール方法を見る

含まれるファイル(1)

  • SKILL.md6.2 KB

SKILL.md(原文)

インストールする前に、エージェントに与えられる指示の中身を確認できます。

Overview

A program status report has one job: give stakeholders the information they need to make decisions or remove blockers, in under 3 minutes. The failure mode is burying the lead - putting good news first and hiding the red items in paragraph 4. The format here front-loads risk and decisions needed, then provides supporting detail. Stakeholders who need detail can read further; those who only need the headline get it immediately.

Workflow

Step 1: Gather inputs

Ask the user for:

  • Program name and reporting period (e.g., "Week of March 3")
  • Overall RAG status (Red / Amber / Green) - if they are not sure, work through it in Step 2
  • Key accomplishments since last report (what shipped, what was decided)
  • Current blockers (what is slowing or stopping the program)
  • Decisions needed from stakeholders (specific asks, not general concerns)
  • Upcoming milestones (next 2-3 checkpoints and dates)
  • Any risks that surfaced or changed this period

If the user provides a narrative or notes, extract these fields from their input before generating the report.

Step 2: Determine the RAG status

If the user is unsure of the overall status, use this rubric:

Green: Program is on track. No unresolved blockers. Milestones will be met as planned.

Amber: Program is at risk. One or more of:

  • A milestone is at risk but there is a recovery plan
  • A dependency is unresolved but expected to resolve within 1 sprint
  • Scope reduction is being discussed but not yet decided

Red: Program is off track. One or more of:

  • A milestone will be missed with no recovery plan
  • A dependency is unresolved with no clear path forward
  • Scope or date change is required and has not been approved
  • A critical team or resource issue has no mitigation

Amber should be used before a problem becomes Red - it is an early warning, not a failure state. Do not use Green if anything requires stakeholder action.

Step 3: Write the report

Use this template exactly:

PROGRAM STATUS - [your program]
Period: [week / sprint / date range]
Updated: [date]
Owner: [your name]

STATUS: [GREEN / AMBER / RED]
[One sentence explaining the status. If Amber or Red, name the specific issue.]

---

DECISIONS NEEDED
[If none, write "None this period."]
1. [Decision needed from whom, by when, and what happens if it is not made]
2. [Next decision if any]

BLOCKERS
[If none, write "No active blockers."]
1. [Blocker description] - Owner: [name] - Target resolution: [date]
2. [Next blocker if any]

---

ACCOMPLISHMENTS (this period)
- [What shipped, what was accepted, what was decided]
- [Keep to 3-5 bullets max. Not every ticket - program-level progress only]

UPCOMING MILESTONES
| Milestone | Target Date | Status |
|-----------|------------|--------|
| [name] | [date] | On track / At risk / Delayed |
| [name] | [date] | [status] |

---

RISKS (new or changed)
[If none, write "No new risks this period."]
- [Risk]: [likelihood] / [impact] - Mitigation: [action and owner]

NOTES / CONTEXT
[Optional: 2-3 sentences of context that stakeholders need. Skip if nothing material.]

Step 4: Apply the three-minute rule

After writing the report, verify:

  • A stakeholder can read the STATUS line and DECISIONS NEEDED section in 30 seconds and know if action is required from them
  • The report is 1 page max when pasted into Slack, email, or a wiki
  • Accomplishments section is 3-5 bullets - not a sprint changelog
  • If anything in the Blockers or Decisions section is more than 2 lines, it is too long - link to a separate doc

Step 5: Calibrate frequency and audience

Recommend the right distribution based on program phase:

  • Weekly: standard for active programs with external dependencies or stakeholder decisions pending
  • Bi-weekly: appropriate for programs in steady-state delivery with no active escalations
  • Daily: only when a program is Red and actively in recovery mode

Audience guidance:

  • Executives / leadership: STATUS + DECISIONS NEEDED only. They do not need the milestone table.
  • Peer teams / dependencies: BLOCKERS + UPCOMING MILESTONES. They need to know what you need from them.
  • Full team: Full report including accomplishments and notes.

Anti-Patterns

1. Green-washing - everything is always green Bad: Status is Green every week until the release is 2 weeks late. Good: Use Amber early. Amber means "we have a plan but it needs attention" - that is valuable signal, not failure.

2. Accomplishments section as a ticket dump Bad: 15 bullets listing every closed Jira ticket. Good: 3-5 program-level progress statements. "Core checkout flow accepted by QA" not "JIRA-1234, JIRA-1235, JIRA-1236 closed."

3. Vague blockers Bad: "We're blocked on infrastructure." Good: "Waiting on cloud team to provision staging environment. Owner: [name]. Target: [date]. If not resolved by [date], release date is at risk."

4. Decisions buried at the bottom Bad: Status report where the decision needed from leadership is in paragraph 6. Good: DECISIONS NEEDED is the second section - immediately after the RAG status line.

5. No cadence - status reports only when things go wrong Bad: Stakeholders only hear from you when there is a crisis. Good: Regular cadence trains stakeholders to expect updates and creates a paper trail. It also normalizes Amber status before it becomes Red.

Quality Checklist

  • RAG status is on the first line with a one-sentence explanation
  • DECISIONS NEEDED section is above accomplishments and milestones
  • Every blocker has a named owner and target resolution date
  • Accomplishments are 3-5 bullets of program-level progress, not ticket lists
  • Report is skimmable in under 3 minutes
  • If status is Amber or Red, a recovery plan or escalation path is stated

レビュー

まだレビューはありません。使ってみた感想をお寄せください。

同じリポジトリのスキル

概要と使いどころ

Rate any product, feature, or experience on the 11-star scale (Brian Chesky's Airbnb thought experiment). Use when user says "rate this experience", "11-star", "star rating", "experience audit", "how good is this", "experience rating", "product audit", "quality assessment", or wants to evaluate product quality and identify improvement paths. Also trigger when user wants to benchmark a feature, assess where a product stands, or map out what "great" looks like - even if they don't explicitly say "11-star".

日本語の概要は準備中です。原文の説明を表示しています。

qa-aman/claude-skills202026年9月10日 更新

Generate A/B copy variants grounded in Eugene Schwartz's awareness and market-sophistication stages and John Caples' tested-headline discipline. Every variant declares its angle, the awareness stage it targets, and a falsifiable hypothesis, and the skill recommends which pair to test first and what delta counts as signal. Use when the user says "A/B test this", "write variants", "give me options", "test different angles", "copy variants", "ab copy", "test this headline", "multiple versions", "which version is better", or wants to test copy before publishing. For reviewing copy that already exists, see copy-review. For sample size and stopping rules, see growth-experiment. For diagnosing a page rather than its words, see page-cro. For full paid ad sets by platform, see ad-campaign-writer.

日本語の概要は準備中です。原文の説明を表示しています。

qa-aman/claude-skills202026年9月10日 更新

Write measurable acceptance criteria for requirements or user stories. Use when the user says "write acceptance criteria", "definition of done", "how do we test this", "fit criteria", "given when then", "Gherkin scenarios", "what does done look like", "testable conditions", "how will we know this works" - even if they don't explicitly say "acceptance criteria".

日本語の概要は準備中です。原文の説明を表示しています。

qa-aman/claude-skills202026年9月10日 更新

Build a strategic account plan for winning, retaining, or expanding a named account. Use when the user says "build an account plan", "strategic account planning", "how do I grow this account", "account expansion strategy", "whitespace analysis", "QBR prep", "key account review", "map the stakeholders in this account", "land and expand plan", "how do I break into [company]", or wants a structured strategy for a specific account.

日本語の概要は準備中です。原文の説明を表示しています。

qa-aman/claude-skills202026年9月10日 更新

Write paid ad copy for LinkedIn, Google, Meta, and YouTube. Produces multiple variants per platform, each targeting a different Eugene Schwartz awareness level and Cialdini persuasion principle. Use when the user asks for ad copy, ad variants, "write LinkedIn ads", Google ads, Meta ads, paid social copy, ad headlines, or wants creative for a paid campaign. Reads brand voice, ICP, and positioning from knowledge/. For organic social posts, see linkedin-post or social-calendar. For the landing page the ad points at, see landing-page-writer. For testing variants, see ab-copy-writer.

日本語の概要は準備中です。原文の説明を表示しています。

qa-aman/claude-skills202026年9月10日 更新

Design clean and consistent APIs. Use when the user says "design an API", "API design review", "design these endpoints", "REST API for X", "GraphQL schema", "API contract", "how should this endpoint work", "review my API design", or wants to create or improve an API interface - even if they don't explicitly say "API design".

日本語の概要は準備中です。原文の説明を表示しています。

qa-aman/claude-skills202026年9月10日 更新

qa-aman のスキルをすべて見る

このスキルの問題を報告する